Project Cost of Blue Line (Line 1)

I was researching the project costs for various metro systems in India and while researching Line 1, I came across two sources quoting two vastly different figures:
1. [https://mmrda.maharashtra.gov.in/en/projects/transport/metro-line-1/overview#gsc.tab=0](https://mmrda.maharashtra.gov.in/en/projects/transport/metro-line-1/overview#gsc.tab=0) which is the official source gives the figure as
|**Total project** **completion cost**|Rs. 2,356 cr.| |:-|:-| |**VGF**|**Rs. 650 cr.**|
If the VGF has not been added already to the project cost, adding it would make the total cost amount to Rs. 3,006 cr. for the project completed in 2014.
2. [https://web.archive.org/web/20130906003741/http://www.hindustantimes.com/India-news/Mumbai/Mumbai-Metro-yet-to-move-fares-move-northwards/Article1-1117620.aspx](https://web.archive.org/web/20130906003741/http://www.hindustantimes.com/India-news/Mumbai/Mumbai-Metro-yet-to-move-fares-move-northwards/Article1-1117620.aspx) this Hindustan Times article from 2013 however states the price as Rs. 4,321 cr. which is a much higher number quoted at a time when the project had not even finished construction. That being said the article doesn't give a breakdown of the costs nor provide any other source for this figure.
Can someone guide me as to which figure is more accurate and which should ultimately be considered authentic, thank you.